Rail Infrastructure Upgrades For Kilmarnock – Dumfries Line

Network Rail engineers have started delivering vital upgrade works on the line between Kilmarnock and Dumfries, work started on Saturday, July 4 and will continue until Sunday, July 12.

Over two miles of new track will be laid and under-track drainage systems improved at a range of locations between New Cumnock and Dumfries.

Work will also be undertaken to strengthen and repair several rail bridges between Cumnock and Dumfries at the same time.

Due to the complexity of the engineering work and the heavy machinery involved, these upgrades cannot be delivered without the short-term closure of the line.

Buses will replace trains between Kilmarnock and Dumfries from Saturday, July 4, to Sunday, July 12.

Alan Ross, Network Rail Scotland’s director of engineering and asset management, said: “Rail plays a key role in keeping freight and people moving across the country and these upgrades are vital to the safe and reliable running of the railway in south-west Scotland.

“Our engineers will be working around-the-clock to complete this complex programme as quickly as we possibly can and to keep disruption to a minimum.“